Brief Description of the Ongoing Projects under ADP 2009-2010
The Chittagong Port being the principal seaport of Bangladesh
handles about 92% of maritime trade of Bangladesh. With the economic
growth of the country and government response towards globalization and
trade liberalization, cargo handling at Chittagong port has been
rising sharply. Because of the steady growth in the volume of
container arriving at the port, the port authority has been
implementing various development programs in phases.
Implementation positions of the ongoing projects included in ADP 2009-2010 are described below:
i) Chittagong port trade facilitation project (ADB funded).
The objective of the project is to increase the capacity of the
container terminals in Chittagong Port and enable it to be at par with
international port security and environmental standards. In the medium
term, the project will lead to reduction in service time; lower
shipping and port charges, which will foster more international trade.
The project is funded by ADB and comprises three main components: i)
CPA Component, ii) CHC (Customs House of Chittagong) Component and
RHD (Roads and Highway Department) Component. CPA Component comprises
the following:
- Reconstruction and up gradation of internal roads and bridge
between CCT and the general cargo berths and improvement of two access
points (gates) to expedite intra-port traffic flow.
- Construction of 900m port-service road and a bridge to provide direct access from the yard to port park.
- Installation of a computerized Container Terminal Management
System(CTMS) including Digital Global Positioning System(DGPS) and up
gradation of the existing management information system.
- Improvement of the port environment and environmental capacity of
CPA by Installing facilities for receiving and separating oil waste
from ships and construction of monitoring office/laboratory etc.
All the components of the project are being executed under 05(five)
packages (CPA-1, CPA-2, CPA-3 & CPA-5) complying ADB’s guidelines.
Out of five packages two packages namely civil work for waste
collection and disposal facility (CPA-3) and port service road 1st
phase (CPA-5) have already been completed. Remaining three packages
such as CTMS and MIS (CPA-1), Oily Waste collection and disposal
Vessel (CPA-2) and reconstruction/up gradation of internal road and
Canal Bridge between the CCT and GCB area and Gate Control equipment
(CPA-4) are in progress.
ii. Construction of Back up Facilities behind Berth # 4 & 5 of New Mooring container terminal
The main objective of the project is to ensure efficient and
full-fledged operation of the newly built New Mooring Container Terminal
(NCT). The DPP of the project with an estimated cost of Tk.114.48
crore was approved by Govt. on 10 November 2008. The consultant for the
project has been appointed and Prequalification (PQ) of the
contractors for civil construction has been completed. Tenders will be
invited shortly from the short-listed contractors.
iii) Construction of Inland Container Terminal (ICT) at Pangaon:
The main objective of the project is to construct a Container River
Terminal at Pangaon, Dhaka for handling containers to be transported
by inland waterways from and to the maritime ports of Chittagong and
Mongla. The second Revised DPP of the project is under process for
Govt. approval at an estimated cost of Tk. 177.57 crores. Bangladesh
Inland Water Transport Authority (BIWTA) with Chittagong Port
Authority (CPA) is implementing the Project in joint venture. The
entire investment cost will be borne by CPA. To this direction an MOU
has been signed between CPA and BIWTA. The implementation work of
the project is in progress and expected to be completed by June 2010.